Badkamer en Toilet renovatie (februari 2012)

Klus en plaatsings werk door

"Klussen bedrijf de Volder"

uit Goirle

jump naar
keukenverbouwing 2010
zolderverbouwing 2012
terug naar Richard's home
__________________________________________________________________________________________________________________________________________________
Dag 15 (9/3): Badkamer gereed + dakraam -- Dag 18 (14/3) Toilet gereed

--
__________________________________________________________________________________________________________________________________________________

Vooraf foto's :

__________________________________________________________________________________________________________________________________________________
Dag 1 (17/2) sloop badkamer + dag 2 (20/2) plaatsing dakraam :

__________________________________________________________________________________________________________________________________________________
Dag3-4 (21-22/2): Badkamer Leidingen, electra, afvoer, framewerk plafond :

__________________________________________________________________________________________________________________________________________________
Dag5 (23/2): Leidingen, afvoer, stuc platen, voorsmeren + Dag6 (24/2): Stuc badkamer :

__________________________________________________________________________________________________________________________________________________
Dag6 (24/2): Toilet tegels + koof weg gehaald + Week 2 : Reconstructie toiletmuurtje / leidingen in muur + stucwerk(dag 13: 8/3) / Toilet achterwand betegeld (dag 16: 11/3)

__________________________________________________________________________________________________________________________________________________
Week 2 (27/2-2/3): Wandtegels badkamer + vloerverwarming + afsmeren :

__________________________________________________________________________________________________________________________________________________
Dag 12 (6/3): Vloertegels voegen, spots, toiletpot, radiator, plafond betimmering toilet :



__________________________________________________________________________________________________________________________________________________
Dag 13-14 (7/3-8/3): Wastafel, glasplaat, afwerken :